Emergency no. +49 711 7812 1220
Hazardous Incident Ordinance info. for Sandhaus Gas Storage Facility & Natural Gas Safety Data Sheet
![](/fileadmin/user_upload/Content/Aktuelles/Aktuell-Bilderpool/Unternehmen/Standorte/terranetsbw_Speicher_Sandhausen.jpg)
Hazardous Incident Ordinance info. for Sandhaus Gas Storage Facility & Natural Gas Safety Data Sheet
Capacity modification network point Lampertheim IV entry
Due to the current low temperatures the firm capacity at the network point Lampertheim IV entry will be increased from 2,000,000 kWh/h to 3,618,000 kWh/h in the period from March 1st 2018 6 o’clock till March 10th 2018 6 o’clock.
MARKET COMMUNICATION WORKS AGAIN
The market communication is working again.
THE MARKET COMMUNICATION IS DISTURBED
We actually have failures with market communication processes. Especially the auction and booking processes via the PRISMA platform, nomination and allocation processes and publications are not working properly.
Terranets bw will immediately inform about alternations of the situation.
We apologize for any inconvenience caused.
MARKET COMMUNICATION WORKS AGAIN
Maintenance work has finished. The market communication is working again.
MAINTENANCE WORK AT THE IT-SYSTEMS OF TERRANETS BW
On December 11th 2017 from 10 a.m. till 2 p.m. will be a scheduled maintenance work at the IT-systems of terranets bw. Within this period of time bookings of capacity at network points from terranets bw and registrations with terranets bw via PRISMA European Capacity Platform will not be possible. Also nomination and allocation processes, publications and EDIFACT-processes will be affected.
We apologize for any inconvenience caused.
THE MARKET COMMUNICATION HAS A BREAKDOWN
We actually have failures with market communication processes. Especially the auction and booking processes via the PRISMA platform, nomination and allocation processes and publications are not working properly.
terranets bw will immediately inform about alternations of the situation.
We apologize for any inconvenience caused.
MARKET COMMUNICATION WORKS AGAIN
The market communication is working again.
Extension of planned maintenance work at Lampertheim IV flow direction entry and exit
The planned maintenance work at the interconnection point Lampertheim IV in both flow directions extends for 3 days till October 17th 2017 6 am. Until then, the capacity trading at this point is suspended. Already booked capacities are not affected by this planned maintenance work.
THE MARKET COMMUNICATION HAS A BREAKDOWN
We actually have failures with market communication processes. Especially the auction and booking processes via the PRISMA platform, nomination and allocation processes and publications are not working properly.
terranets bw will immediately inform about alternations of the situation.
We apologize for any inconvenience caused.
MARKET COMMUNICATION WORKS AGAIN
The market communication is working again.