Pursuant to the ruling BK9-19/610 (REGENT 2021) of the Bundesnetzagentur the capacity fees for a firm freely allocable capacity with a term of one year for interconnection and storage-network points to be applied as of January 1st 2023 amounts to 4,82 €/(kWh/h)/a.
Pursuant to the ruling BK9-19/610 (REGENT 2021) of the Bundesnetzagentur the preliminary capacity fees for a firm freely allocable capacity with a term of one year for internal order points and ultimate consumer points to be applied as of January 1st 2023 amounts as well to 4,82 €/(kWh/h)/a.
Compared to 2022, the tariff for booking firm freely allocable entry and exit capacities will be around 37 percent higher.
Due to the geopolitical situation, it was assumed that gas flows would change in some cases and that the market would consequently adjust its booking behavior. In addition, the significant increase in the cost of fuel gas will also lead to an increase in the fee.
Pursuant to § 6 (5) of the Cooperation Agreement between the operators of gas supply grids in Germany as amended on March 31th 2021, effective from October 1st 2021 (Cooperation Agreement XI – German KoV XII) the final capacity fees for these points will be published until December 2nd 2022 at the latest.
The capacity fee for a firm freely allocable capacity is valid from 1 January 2023 to 1 January 2024.
According to ongoing appeals procedures against REGENT the tariff may be adjusted. terranets bw GmbH will inform as soon as any relevant information is available.