To get initial information regarding a network connection to the transmission system of terranets bw, please write an email to netzanschluss[at]terranets-bw.de.
To send a binding enquiry to terranets bw in order to run the tests required for a gas connection commitment, please complete and send the form below to: netzanschluss[at]terranets-bw.de
Upon receipt of your network connection enquiry, we at terranets bw inform you without delay of the costs related to handling your enquiry. We also inform you about which further documents are needed for the tests.
Upon receipt of the complete documents, the tests required for a connection commitment are carried out (e. g. capacity simulation, capacity calculation and evaluation, rough routing, connection options). This results in a test report including a cost estimation for implementing the network connection.
If you decide in favour of implementing the network connection, we draft the contractual basis prior to beginning the planning and construction of the network connection.
These contracts regulate the essential technical and legal conditions for the gas delivery/offtake, thus providing a sound base for cooperation.
Netzanschlussvertrag
Netzkopplungsvertrag
Richtlinien terranets bw
Anlage 1
Anlage 2
After concluding the network connection contract or network coupling contract, we immediately initiate the necessary measures for implementing the network connection.